Serving Southeastern North Carolina since 1999
CHOOSE A PROJECT/year BELOW
Each expandable section below showcases the ECC projects for that calendar year. Clicking the “+” will expand the project details and photo gallery.
2023 PROJECTS
The Vice site included clearing and demo, erosion control, grading and storm drain.
Click images below for larger views.
The Library site included clearing and demo, erosion control, grading and storm drain.
Click images below for larger views.
Starway Village has included demolition of existing structures, erosion and sediment control, water, sewer, roof drain and storm drain installations. It also included asphalt (including stone base and curb & gutter).
Click images below for larger views.
UNCW Walton Facilities included clearing, erosion control, grading and infrastructure (roof drain and storm drain) installation for the athletic facilities and dewatering a pond for bridge construction.
Click images below for larger views.
2022 PROJECTS
7-11 in Leland site included minor clearing, grading, erosion control, water, sewer and storm drain installations. Asphalt paving, curb & gutter, ADA compliant sidewalk, fuel pads, drop inlet frame and grates for car wash drain.
See Home page Video Section for drone footage.
This community included clearing, erosion control, earthwork, water, sewer and storm drain installations. It also included retaining walls, asphalt paving, striping, curb and gutter.
Click images below for larger views.
The College Acres Drainage Project was extensive including clearing, grubbing, tree harvesting, existing storm drain removal, diversion of current storm drain to improved storm drain construction. Fence and retaining wall removals and replacements. Drop inlet installations.
Click images below for larger views.
This subdivision work included clearing and demo, erosion control, grading, water, sewer, storm drain installation. Ashpalt paving, curb & gutter and retaining walls.
Click images below for larger views.
Middle Creek Subdivision included erostion control, grading, water, sewer, storm drain installations as well as a lift station. Asphalt paving, striping, signage, curb and sidewalks. Retaining walls.
Click images below for larger views.
Petco included minor clearing, grading, erosion control, water, sewer and storm drain installations. Asphalt paving, curb & gutter, ADA compliant sidewalk.
This retirement community included clearing, grading, erosion control, water, sewer and storm drain installation and asphalt paving.
Click images below for larger views.
Walker Napa sitework included clearing & demo, grading, water, sewer and storm drain installation, as well as asphalt paving with curb, gutter and sidewalks.
2021 PROJECTS
Clearing, grading, water, sewer, storm drain installation as well as retaining walls, asphalt paving and sidewalks, curb & gutter.
Click images below for larger views.
minor clearing and excavation for pool facilities, water, sewer and storm drain.
Click images below for larger views.
Kitty Hawk project included clearing, grading, erosion control, water, sewer and storm drain installation as well as asphalt, curb and gutter.
Installation of force main line.
Palmetto Creek included grading and storm drain installation.
Project included minor clearing, grading, water, sewer and storm drain installation as well as paving.
This project included water and sewer line installation.
This project included storm drain installation.
Waterstone project included clearing and demo, erosion control, grading, water, sewer and storm drain installation. Asphalt paving and construction of a Pickleball Court.
2020 and Prior PROJECTS
This project included the replacement or abandonment of 24 air release valves, isolation gate valves, vacuum relief valves, blowoff gate valves and misc. door repair or replacement for below grade structures. Replacement of flowmeter and surge relief valve at pump station, demo abandoned pump station and existing raw water piping and install new raw water piping and supports.
This project is an existing apartment complex where we installed new sanitary sewer lines, repaired existing leaking storm drains, performed all erosion control, traffic control, demolition of existing storm drains, curb & gutter and asphalt.
Demolition, Grading, Storm Drain, Roof Leaders, Sanitary Sewer, Water, Curb & Gutter, Asphalt and Concrete Paving.
Jefferson Landing, now known as Brunswick Forest located in Leland in Brunswick County. Our work included water and sewer installation with over 12,000 lf of sewer installed in depths at times greater than 20’.
Tidal Walk is located on Myrtle Grove Rd. in New Hanover County. Our work included water, sewer and storm drain installation with over 9,000 lf of gravity sewer installed in depths at times greater than 20’ and over 8,700 lf of force main sewer. Jack and Bore and Directional Bore methods were used in some of the installations.
Woodlake @ Lord’s Creek is located off of River Road in New Hanover County. Our work there consisted of complete site development, water, sewer and storm drain installations. We installed more than 11,000 lf of gravity sewer at times in depths greater than 30’.
North Campus Regional Lift Station is located in New Hanover County. This project is the construction of 990 LF of 10 inch gravity sewer, 3,250 LF of 12 inch gravity sewer, 1,305 LF of 14 inch gravity sewer, 980 LF of 24” gravity sewer, 1,550 LF of parallel 12 inch and 18 inch force mains, a 728 GPM pumping station with 20’ x 25’ Cast In Place Wet Well, Electrical building, all weather access road, site work and SCADA system installation and integration.
This project was to replace the storm water system. Work includes adjustments to water 6″-8″ DIP 475 LF and sewer utilities 8″ DIP 4,600 LF, 12″-18″ DIP 494 LF, 93 MH’S, installing RCP piping ranging in size between 18″-48″ in diameter 9,162 LF and installing concrete box culverts sized 5’x2′. Included are all manholes, connections to existing piping, repaving streets, reconstructing curb & gutter, sidewalk and driveways, demolition, abandonment of pipelines and all other work required to complete the work.
Construction of a multi-use trail from Randall Parkway to Mallard Dr. includes sidewalks and bicycle lanes for the City of Wilmington in coordination with UNCW and NCDOT. Work includes asphalt paving, concrete, erosion control, hauling, excavating, grading, pavement markings, traffic control, storm drain, signage, fencing, utilities, landscaping and irrigation. Includes 12″-24″ RCP Storm drain.
Work includes clearing and grubbing, erosion and sediment control, tree protection, removal of existing underground utilities, site grading, excavation, retaining walls, filling and compaction, sanitary sewer, storm sewer, site water systems, curb & gutter, stone base and paving and pavement markings, pervious concrete.
Complete site work package including, earthwork, erosion control, site demolition including tree, concrete asphalt, water, sewer and storm drain removal. Replacement and installation of drainage system with piping from 12″ – 60″, roof drain piping, temporary sediment basins, sewer and water. 60″ RCP STORM DRAIN 376 LF, 12″-36″ RCP STORM DRAIN 576LF, 4″-8″ CPP 1,580 LF, Construction of vehicular bridge.
Installation of approx. 80,000 ft. of 24″ – 6″ water supply transmission mains, potable watermains and concentrate lines. 30″ – 18″ Jack and Bores, 8″ – 6″ Horizontal Directional Drills, installation of an outfall diffuser structure with directional drill under a lagoon and creek into the New River. Complete with all appurtenances and all associated site work.
Our work on this project consists of demolition, clearing, removal of demo material, tree protection, traffic control, intersection improvements, erosion control, temporary seeding, construction entrance, all excavation, grading, cut/fill, import/export, fine grading, topsoil spreading, including curb backfill, all compacted subgrade, all asphalt work including drive aprons and intersection improvements, complete segmental block retaining wall including all backfilling, complete storm drainage system including all storm structures, piping, pipe bedding, fittings and connections, storm water wetlands, roof drain piping and connections, rip rap, complete water and sewer installation.
Contract – $400K – $500k
Complete Site Development including Demo, Clearing, Grading, Water, Sewer, Storm Drain, Landscaping, Fencing, Curb & Paving, Guardrails, Soundwalls, Retention Ponds Contract $8M-$8.5M
Our work on this project included water, sewer, storm drain, concrete, keystone retaining walls, jack and bore, all earthwork operations and asphalt and pervious concrete paving, concrete sidewalks and curb and gutters.
Contract – $2.5M – $3M
Throughout Compass Pointe’s different phases our work consists of Grading, Storm Drain and Structures, Water, Sewer, including a lift station, Irrigation, Conduits, placing stone, installing curb and gutter, sidewalks and asphalt including the turn lane on the west entrance.
This project included the replacement or abandonment of 24 air release valves, isolation gate valves, vacuum relief valves, blowoff gate valves and misc. door repair or replacement for below grade structures. Replacement of flowmeter and surge relief valve at pump station, demo abandoned pump station and existing raw water piping and install new raw water piping and supports.
Hours:
Mon – Fri: 7am to 5pm
Appointment recommended
Saturday/Sunday: Closed
After Hours By Appointment
Site powered by SEO Counselors